We’ve been fielding a lot of questions lately about the timeline for the sale of Grace Lake South lots. Earlier today we received the following update from Jeff Humble, Director of Planning and Development at the City of Yellowknife:
“Public Works is working on the road profile which will provide the basis for the layout and construction costs. Once we have that piece we will be able to prepare a “draft” Development Scheme and Rezoning Amendment. This will likely take us into spring. With these by-law amendments a public hearing is required and Council needs to approve the marketing plan to establish lot prices and advertise the ballot draw.